this article discusses the modeling of the production process-using network planning for a project to carry out repair work based on the definition of critical work. The optimization algorithm of the network model allows the adjustment of time resources and to identify the most intense work. Any impact on the timing of critical work directly affects the timing of the implementation of the entire complex of work of the project under consideration Optimization allows you to regroup resources and make recommendations on the choice of control parameters of the project, allowing you to optimize the structure of the model before its implementation.